Idea

Requirement Output (2Day)
Requirement Documents (1Day)
Pre-PA(Project Approval) Review (1Day)
Pre-PA(Project Approval) Review (1Day)
Design

ID Design (6Day)
ID Design (4Day)
ID Review (1Day)
Update ID Design
Mock-up & Confirm ID (1Day)
ID Review (1Day)
Update ID Design
Mock-up & Confirm ID (1Day)
Structure Design (8Day)
Structure Design (4Day)
Structure Review(R&D) 1st (1Day)
Update Structure Design (1Day)
Structure Review+B11:C21(R&D+PM) 2nd (1Day)
Design Documents Output (1Day)
Structure Review(R&D) 1st (1Day)
Update Structure Design (1Day)
Structure Review+B11:C21(R&D+PM) 2nd (1Day)
Design Documents Output (1Day)
Quotation

Submit Quotation (3Day)
Raw Material Enquiry(2Day)
(1Day)
(1Day)
Prototype Sample

Prototype Sample (9Day)
Structure&Hardware&Software Purchase (6Day)
Assembly Test (1Day)
Structure Adjustment
Structure Verification
Prototype Sample Review (1Day)
Confirm Sample
Assembly Test (1Day)
Structure Adjustment
Structure Verification
Prototype Sample Review (1Day)
Confirm Sample
Molding

Start-Up
Project Evaluation Meeting (1Day)
Project Schedule (1Day)
Project Schedule (1Day)
Mold
Mold Design Evaluation (2Day)
Mold Drawing Output (1Day)
Mold Development (25Day)
Mold Verification (1Day)
(5Day)
Surface Treatment (5Day)
Mold Drawing Output (1Day)
Mold Development (25Day)
Mold Verification (1Day)
(5Day)
Surface Treatment (5Day)
Atomize

Core Technology
Main Heating Coil Teachnology Select (3Day)
Flavors/Taste Verification (5Day)
Flavors/Taste Verification (5Day)
EP

Engineering Verification Test
Raw Material Purchase (7Day)
Initial Sample Assembly (1Day)
Sample Verification Test 1st (1Day)
Sample Adjustment (5Day)
Sample Verification Test 2nd ... (1Day)
Initial Samples Pass Test (4Day)
Initial Sample Assembly (1Day)
Sample Verification Test 1st (1Day)
Sample Adjustment (5Day)
Sample Verification Test 2nd ... (1Day)
Initial Samples Pass Test (4Day)
PP

Pilot Production
Raw Material Purchase (11Day)
Final Sample Assembly (1Day)
Sample Verification Test 1st (5Day)
Sample Adjustment
Sample Verification Test 2nd ...
Samples Pass Test (1Day)
Failure Analvsis
Final Sample Assembly (1Day)
Sample Verification Test 1st (5Day)
Sample Adjustment
Sample Verification Test 2nd ...
Samples Pass Test (1Day)
Failure Analvsis
MP

Mass Production
Order (12Day)
Raw Material Purchase (1Day)
Products Assembly (7Day)
Packing
Raw Material Purchase (1Day)
Products Assembly (7Day)
Packing
Shipping